Temecula City Council calls for repaving Pauba Road and Butterfield Stage Road

544
File photo
Pauba Road and Butterfield Stage Road will be repaved.A 4-0 Temecula City Council vote April 27, with mayor Maryann Edwards abstaining due to the proximity of the improvements to her property, approved the specifications for the road rehabilitation work, authorized the county’s Department of Public Works to solicit construction bids, and found the project categorically exempt from California Environmental Quality Act review.The work will rehabilitate the full width of Pauba Road from Margarita Road (other than the intersection) to Butterfield Stage Road and will rehabilitate the full width of Butterfield Stage Road from 405 feet south of De Portola Road to 230 feet south of Rancho California Road. The rehabilitation will consist of the cold milling of two to 3 inches of the exist