Gannett Fleming awarded EVMWD construction oversight contract for Tomlin Pipeline replacement

The Elsinore Valley Municipal Water District awarded Gannett Fleming Inc. the construction management and observation services contract for the Tomlin Pipeline replacement project.A 3-0 EVMWD board vote Thursday, July 28, with Andy Morris and Harvey Ryan absent, awarded Gannett Fleming a $549,152.23 professional services contract. The board authorized a total appropriation of $551,898.23 which also covers $2,746 for overhead.The Tomlin Pipeline was constructed in 1964 and is currently a steel water main 6 inches in diameter. Most of the pipeline was constructed within a dirt roadway, and it is within a utility easement 20 feet wide. Erosion along the alignment has caused parts of the pipe to become exposed to the elements, which has caused corrosion issues and is compromising the s