The County of Riverside approved two change orders to the construction contract for the extension of Clinton Keith Road from Leon Road to State Route 79.A 4-0 Riverside County Board of Supervisors vote Dec. 13, with Manuel Perez absent, approved the change orders to the contract with Security Paving Company Inc. The change orders will add $2,282,090 to the contract amount.On Jan. 11 the county supervisors awarded Security Paving Company, which is headquartered in Westlake Village, the construction contract to extend Clinton Keith Road from Leon Road to State Route 79. The original contract was for $23,569,634. A separate Jan. 11 vote approved an agreement between the county and the City of Murrieta addressing Max Gilliss Boulevard roadway improvements which are part of the construc




