EMWD approves rehabilitation contract for Well 33

The Eastern Municipal Water District approved a construction contract to rehabilitate Well 33. The EMWD board voted 3-0 April 3, with Phil Paule and Randy Record absent, to award a $355,620 contract to General Pump Company, Inc. The board action approved total appropriations of $409,000 which will also cover $16,500 for EMWD staff time and a $37,280 contingency. Well 33 is at Mountain Avenue West and 7th Street within the San Jacinto city limits. EMWD staff identified Well 33 as requiring rehabilitation during Fiscal Year 2023-24 due to the number of years since the well’s previous inspection and a loss of production capacity. General Pump Company, whose headquarters office is in San Dimas, is one of Eastern’s pre-approved well maintenance contractors. In November 2023 General Pump