Ferreira Construction to rehabilitate Menlo Lift Station

Ferreira Construction was awarded the Eastern Municipal Water District contract to rehabilitate the Menlo Lift Station.The EMWD board voted 5-0 on February 5 to award a $1,014,000 construction contract to Ferreira Construction for the work. Krieger & Stewart Consultants, Inc., was given a $163,000 contract for engineering services during construction. The total $1,775,000 of appropriations approved by the board also includes inspection, geotechnical services, and EWMD staff costs along with $159,200 of contingency budget.The Menlo Lift Station at the intersection of Cawston Avenue and Seattle Street was constructed in 1989. A recent inspection determined the wetwell piping and valve assembly to be approaching the end of their useful life due to corrosion. In July 2023 Eastern c