The Elsinore Valley Municipal Water District will be upsizing the pipeline along Diamond Drive, and two 5-0 votes at the May 23 EVMWD board meeting approved contracts to upsize that blending line.
One motion approved a $1,935,547 public works contract with WEKA, Inc., for construction of the facilities while the other action authorized a $303,551 construction management contract with Hoch Consulting. The action approving the construction contract authorized total expenditures of $2,027,954 which will include $82,729 for staff time and $9,678 for overhead. The construction management contract has total authorized expenditures of $305,069 including $1,518 for overhead.
The Elsinore Valley Municipal Water District operates ten groundwater wells in the Elsinore Valley Subbasin which have an